NO.1 The Risk of NOT meeting project quality objectives:
A. considered a long term risk.
B. can be minimized through continuous monitoring.
C. All of the other alternatives apply.
D. will be reflected in the "in-service" life of the product or service.
E. Considered a long term risk and will be reflected in the "in-service" life of the product or service.
Answer: C

PMI模試   PMP試験   PMP   PMP難易度

NO.2 Which is not an example of a correctly handled Contract closure procedure?
A. Early termination of a contract because of arepudiatory breach
B. Settling and finally closing the contract agreement
C. Early termination of a contract because of an immaterial breach
D. Product verification by stakeholders and administrative closure
Answer: C

PMI的中率   PMP対応   PMP種類   PMP

NO.3 Key Management skills include:
A. Negotiating
B. All of the other alternatives apply
C. Leading
D. Communicating
Answer: B

PMI最新版   PMPトレーニング資料   PMP教科書   PMP学習教材
Explanation:
All options are key management skills.

NO.4 You are in the process of monitoring the various project processes and their performance.
Which of the following are you LEAST concerned with during this process?
A. Reviewing and approving all recommended corrective and preventive actions
B. Providing forecast to update current schedule information
C. Assessing information to determine whether corrective actions are necessary
D. Comparing actual project performance against project management plan
E. Analyzing and tracking project risks
F. Monitoring the implementation of approved changes
Answer: A

PMI   PMP   PMP学校

NO.5 During what Time Management Process are the specific activities that must be performed to
produce the deliverables in the WBS identified and documented?
A. Estimate Activity Durations
B. Define Activities
C. Sequence Activities
D. Develop Schedule
Answer: B

PMIサービス   PMP組織   PMP赤本

NO.6 A company is about to begin work on a large construction project to build four new buildings
for a bank that wants to open new branches. The sponsor is writing a project charter. She recalls that
a previous project the company performed for another bank ran over budget because the team had
underestimated the effort required to install the reinforced walls in the vault. The previous project
manager had documented the details of the lessons learned from this project. Where should the
sponsor look for these lessons learned?
A. The company's organizational process assets
B. The project records management system
C. The project's work performance information
D. The project's performance reports
Answer: A

PMIソフトウエア   PMP問題   PMP参考書   PMPクエリ
Explanation:
Lessons learned from past projects are always part of a company's organizational process assets, and
are usually stored in a process asset library. The other three answers are important project tools, but
they're not where you find lessons learned.

NO.7 During execution of a project, the most common source of conflict within the project team is
likely to be:
A. Schedules
B. Priorities
C. Technical opinions
D. Cost
Answer: A

PMIテスト   PMP   PMP特典

NO.8 Which of the following statements are true?
A. Contract closure and administrative closure both involve quality assurance activities
B. Contract closure and administrative closure both involve scope verification
C. Contract closure and administrative closure both involve benefit cost analysis
D. Contract closure and administrative closure both involve product verification
Answer: D

PMIサービス   PMP認証試験   PMP   PMPディレクトリ同期   PMP過去問題

PMIのPMP試験に受かることは確かにあなたのキャリアに明るい未来を与えられます。PMIのPMP試験に受かったら、あなたの技能を検証できるだけでなく、あなたが専門的な豊富の知識を持っていることも証明します。JapanCertのPMIのPMP試験トレーニング資料は実践の検証に合格したソフトで、手に入れたらあなたに最も向いているものを持つようになります。 JapanCertのPMIのPMP試験トレーニング資料を購入する前に、無料な試用版を利用することができます。そうしたら資料の高品質を知ることができ、一番良いものを選んだということも分かります。

JapanCertが提供したPMIのPMI-RMPトレーニング資料を利用してから試験に合格することがとてもたやすことになって、これは今までがないことです。これは試験に合格した受験生の一人が言ったのです。JapanCertが提供したPMIのPMI-RMPトレーニング資料はあなたの雑然とした考えを整理できます。そうしたらあなたは心理的なストレスを減らせるだけでなく、気楽に試験に受かることもできます。JapanCertには一部の問題と解答を無料に提供して差し上げますから、もし私の話を信じないのなら、試用版を使ってみてください。利用してみたら効果があるかどうか自分でよく知っているようになります。あなたに絶対向いていると信じていますよ。

PMP試験番号:PMP 実際試験
試験科目:「Project Management Professional」
最近更新時間:2015-10-27
問題と解答:3615

>> PMP 実際試験

 
PMI-RMP試験番号:PMI-RMP 科目対策
試験科目:「PMI Risk Management Professional」
最近更新時間:2015-10-27
問題と解答:273

>> PMI-RMP 科目対策

 

君はまずネットで無料なPMIのPMP試験問題をダウンロードしてから 弊社の品質を確信してから、購入してください。JapanCertは提供した商品は君の成功を全力で助けさしたげます。

購入前にお試し,私たちの試験の質問と回答のいずれかの無料サンプルをダウンロード:http://www.japancert.com/PMP.html